Project Post-Mortem
The project I was working on involved a
new product being made by a company I was working for. Most of our product team (including the
Project Manager (PM)) was new to project management so there was a steep
learning curve. I supported the project
by providing technical advice to ensure it could be serviced by a technician
with the least time and cost to service, repair or replace components. When reviewing the Generic Project Life Cycle
Phases (Greer, 2010) ,(pp 42-43). Phase 1 passed the first question because it
was determined that there was a need and the project was feasible. It failed the second question. In the beginning of the project there were no
unnecessary deliverables, but that changed after launch. Phase 2 was to Create a Project Plan. This company wanted estimates to be
realistically close to what the team thought actual costs would be. Since most of the team was new, we
complied.
This is where Phase 2 started to fall
apart. The product manager wanted to add
items after launch that should have been stopped. If they had been part of the original plan,
money could have been incorporated in the estimate to cover them. I learned from this that there is almost no
way to stay on budget if the PM doesn’t stop scope creep. Scope creep is very common (Laureate
Education (Producer), n.d.) . There were several times the group let scope
creep in because each idea sounded good and would have benefitted the project. Add to this, people from senior management
wanted some of the scope creep items added to the project. We were new to this and thought the ideas
would benefit the project and the company.
Some of them made the project more successful but added a few months to
the project and about $20,000 dollars in extra cost. Fortunately, senior management approved this
because they had asked for the extra items to be added to the project.
Phase 3 also started well in that product
specifications were detailed in the beginning of the project. The different departments involved in the
project were represented and the different players provided valuable input into
the project. We could have improved the
work process by meeting with senior management and the product director at the
same time and asking about any added features they wanted. We could have then discussed the
ramifications of adding features and how they should be documented and approved
by the team and by senior management using a document called a Change of Scope
document (Laureate Education (Producer),
n.d.) . This would have kept us on track because the
time and cost would have been changed and approved by all involved in the
project.
Phases 4 (Create Deliverables) and 5 (Test
and Implement Deliverables) followed the path of scope creep. As parts of the project were completed,
additional features were added due to scope creep. These features needed to be speced, added and
tested. This is where time and money
were added to the project. The outcome
was a project that worked well and fit a market niche. It has sold well, so the company was able to
recuperate the money spent on the extra features, which is fortunate. The project taught all involved a valuable
lesson about adding features after a project has been scoped. They started using the Change of Scope
document more and more.
References
Greer, M. (2010). The Project Management
Minimalist:Just Enough PM to Rock Your Projects! Retrieved from
michaelgreer.biz: http://michaelgreer.biz/?page_id=636
Laureate Education (Producer) (Director). (n.d.). PM
Concerns: Scope Creep [Motion Picture].
No comments:
Post a Comment